The NEC – CoACH PARK

Our client approached NMC to restore a dilapidated coach parking area at the NEC in Birmingham. Following a recent meeting at a supplier day our client awarded NMC this project because of our experience and capabilities particular with surfacing and drainage.

Project Key Stats

3 days

On-site Duration

1,450 sq/m

Total Site Area

Project Overview

Our client approached NMC to restore a dilapidated coach parking area at the NEC in Birmingham. Following a recent meeting at a supplier day our client awarded NMC this project because of our experience and capabilities particular with surfacing and drainage.

As turnkey car park maintenance experts, specialising in Surfacing, Drainage and Civil Engineering, NMC were awarded this project at the NEC. The site condition was extremely poor with the surface course wearing in the coach park, poor drainage and particular problems with the drainage channel system that was insufficient for its requirements. The client requested NMC to complete the following elements of this project, resurfacing the 1,450m² coach park with a new surface course, drain cleansing and installing new heavy duty drainage channels that are fit for purpose, replacing the smaller drainage channels that were currently on site and causing problems.

Delivery

Traffic management was put in place to ensure the works would be carried out safely, segregated from the public and traffic ensuring safety and security.
The works were completed over three days separating the works into a day to cleanse the drains and install the F900 linear drainage system and a day to plane and resurface the 1,450m² coach park with an SMA 10 HS asphalt.
Completed to schedule the site was handed back to a very happy client.

“Superb job, fantastic communications and delivery, I am very impressed with NMC” – Brian Etheridge – Contract Manager