Harvey Centre, Harlow

Our client required a full repair to be carried out on the upper deck of their multi-storey car park in a busy town centre shopping mall. The client wanted to use the repair as an opportunity to increase parking bays where possible.

Project Key Stats

months

On-site Duration

3,600 sq/m

Total Site Area

Project Overview

Services Delivered

Objective

The upper deck had developed hairline cracks allowing water to seep up through to the deck below. The reinforcement bar was also starting to show signs of corrosion. The 3600m2 area required a complete repair and included resurfacing and lining.

Delivery

The upstands and edge work required grinding and a 460 planer was used to remove the resin from the concrete deck. After the deck had been smoothed, cleaned and primed, we prepared the hairline cracks and expansion joints in readiness to receive the membrane. All bays and roadways were body coated and sanded. Once these were dry and the excess sand swept we colour coated and white lined the area.

Following completion of the upper deck we removed the rusted rebar, gaining access from the deck beneath, we cleaned and primed these areas and fitted adenoids to prevent further corrosion. We were then able to undertake the restoration of the concrete.

Project Gallery

Ready for a Site Survey?